Home › Answers › Engineering Assignments › AE6005 Report 2 Sample: A320 Base Maintenance Planning

AE6005 Report 2 Sample: A320 Base Maintenance Planning

DA

Diploma Assignment Help UK Editorial Team

Assignment Expert

4 min read
November 06, 2026

For information and reference only – not to be submitted as your own work.

This AE6005 sample extract shows how a group might approach the second Kingston University AE6005 report: a 2,000-word planning report for a ten-year A320 base maintenance solution. It follows the structure set out in the AE6005 Aircraft Maintenance Report 2 brief and is abridged: the task list, network and register are shortened, and every operator figure, duration and cost is illustrative rather than taken from a real airline. For the method behind each section, see our guide on how to write an A320 base maintenance planning report.

Planning table

Brief part Suggested words What markers look for
Introduction, aims, objectives, deliverables (20 marks) 350–400 Clear scenario, measurable objectives, deliverables tied to the ten-year horizon
Task list and Gantt chart or AON network (40 marks) 700–800 Logical work breakdown, dependencies, durations, named owners, critical path
Communication plan (10 marks) 200–250 Who, what, when, how; escalation route; fit to a multi-site team
Risk register (15 marks) 300–350 Specific risks, likelihood and impact scoring, owners and mitigations
Summary (5 marks) 100–150 Recommendation and next steps, no new material
Readability (10 marks) Whole report Consistent layout, labelled figures, Harvard referencing

Check your own brief and module handbook for the exact word limits, what counts towards the total and the group and individual submission rules.

If you want a planning report built around your own group scenario, our engineering assignment help team can scope it with you.

Introduction, aims, objectives and deliverables

Scenario

The scenario assumes a UK-based operator running a fleet of A320-family aircraft on short-haul routes. The operator needs a ten-year base maintenance solution that covers heavy checks, line support at outstations and component support, while keeping aircraft availability high. The fleet size, hub location and check slots used below are illustrative assumptions, stated so that every later figure can be traced back to them.

Base maintenance for this fleet is performed under an approved maintenance programme, with scheduled tasks and intervals defined by the operator’s programme, which is normally derived from the manufacturer’s maintenance planning data and approved by the competent authority (UK Civil Aviation Authority, 2024; Kinnison and Siddiqui, 2013). This report does not set check intervals; it plans the project that delivers the capability to carry them out.

Aim and objectives

Aim: to plan the selection, set-up and mobilisation of a ten-year A320 base maintenance solution that meets the operator’s availability and airworthiness requirements.

  1. Define maintenance requirements for the fleet over ten years from the approved programme.
  2. Appraise three delivery options: in-house hangar, outsourced Part-145 provider, and a hybrid arrangement.
  3. Assess facilities, equipment and personnel needed at the hub, base and outstations.
  4. Produce a task list, network diagram, communication plan and risk register for mobilisation.

Option appraisal

A short weighted comparison shows how the group reached its preferred option. Weights and scores are illustrative team judgements, not operator data.

Criterion Weight In-house Outsourced Hybrid
Control of slots and quality 30% 5 3 4
Capital exposure 25% 1 5 3
Skills and labour availability 25% 2 4 4
Flexibility over ten years 20% 2 3 5
Weighted score 100% 2.75 3.75 4.00

The hybrid option scores highest: base checks go to an approved Part-145 organisation, while the operator keeps line support and planning in-house. The organisation must hold a maintenance approval from the relevant authority, such as EASA or the UK CAA, and the operator remains responsible for continuing airworthiness management (European Union Aviation Safety Agency, 2024; UK Civil Aviation Authority, 2024).

Deliverables

Deliverables are the signed provider contract, an approved work package structure, trained and authorised staff, tooling and spares agreements, and a first-check readiness review. Each is linked to a milestone in the network below.

AE6005 sample task list and network diagram

Work breakdown and task list

The group broke the project into five work packages: governance, provider selection, facilities and equipment, people and training, and readiness. Durations are in weeks and are illustrative planning estimates, in the style of a three-point estimate averaged for each task (Kerzner, 2022).

ID Task Predecessor Duration (weeks, illustrative) Owner role
A Confirm requirements from maintenance programme – 4 Planning engineer
B Issue tender and appraise options A 8 Project manager
C Audit shortlisted providers B 6 Quality lead
D Negotiate and sign contract C 10 Commercial lead
E Define work package and task card structure A 6 Planning engineer
F Agree tooling, GSE and spares pooling D, E 8 Logistics lead
G Staff authorisations and training plan D 12 Human resources lead
H Set up records and IT interface D, E 10 Systems lead
I Readiness review and first-check induction F, G, H 4 Project manager

Network analysis

Plotted as an activity-on-node network, the forward pass gives the following earliest finish times: A 4, B 12, C 18, D 28, E 10, F 36, G 40, H 38 and I 44 weeks. The critical path is A–B–C–D–G–I at 44 weeks, with float of four weeks on F and two on H (Kelley and Walker, 1959). In the submitted report, the group’s diagram would be drawn as a figure, with each node showing ID, duration, earliest start and finish, and float.

The critical path runs through contracting and training, so any slip in the contract or in staff authorisation moves the first check date. The group therefore ring-fenced the commercial lead’s time and started authorisation paperwork as soon as the contract terms were agreed.

If the module expects a Gantt chart rather than a network, the same table converts directly: bars for each task, dependency arrows and a milestone marker for contract signature and for readiness review. Whichever format you choose, name the owner of each task, since the brief asks for allocation.

Communication plan

The team spans several sites, so the plan favours short, regular and recorded communication. Frequencies below are illustrative.

Audience Content Method Frequency Owner
Project team Progress, blockers, actions Online stand-up Weekly Project manager
Sponsor and operator management Milestones, cost, top risks Written status report Fortnightly Project manager
Provider and suppliers Work package scope, slots, parts Planning meeting and shared tracker Fortnightly Planning engineer
Quality and regulator liaison Audit findings, approvals Formal correspondence As required Quality lead
Outstation line teams Changes to procedures and handover Briefing note Monthly Logistics lead

Issues that threaten a critical-path task are escalated to the project manager within one working day and to the sponsor within three. Decisions are logged in a shared register so that every member can evidence their contribution to the individual logbook (Project Management Institute, 2021).

Risk register

Likelihood and impact are scored from 1 to 5 and multiplied, following the general approach of identifying, analysing and treating risk in ISO 31000 (International Organization for Standardization, 2018). Scores are illustrative team judgements.

ID Risk L I Score Mitigation Owner
R1 Provider hangar slots unavailable in peak season 4 4 16 Reserve slots in contract; agree a backup provider Commercial lead
R2 Shortage of certifying staff 3 5 15 Early recruitment; training pipeline; contract cover Human resources lead
R3 Delay in approval or audit findings 3 4 12 Early audit; agreed corrective action plan Quality lead
R4 Spare parts lead times extend turnaround 4 3 12 Pooling agreement; forecast from task cards Logistics lead
R5 Records system incompatibility 2 4 8 Interface testing before first check Systems lead
R6 Currency or cost escalation over ten years 3 3 9 Indexed price clauses; annual review Commercial lead

R1 and R2 exceed the group’s action threshold of 15 and are reviewed weekly. The register is a living document, so each fortnightly status report updates the scores.

Summary

The group recommends a hybrid delivery model, with base checks at an approved Part-145 provider and planning and line support kept in-house. The mobilisation plan runs for an estimated 44 weeks on the critical path through contracting and staff authorisation, and the principal risks are slot availability and certifying staff. Next steps are to confirm the programme requirements with the operator, begin the tender and validate the illustrative durations with the chosen provider.

If you are building a similar plan, our report writing help covers structure and referencing, and you can send your brief through the assignment submission page. For the earlier, different task in this module, see our AE6005 landing gear network analysis sample and the matching critical path analysis guide.

References

European Union Aviation Safety Agency (2024) Part-145 – Maintenance organisation approvals. Available at: https://www.easa.europa.eu/en/acceptable-means-compliance-and-guidance-material-group/part-145-maintenance-organisation-approvals (Accessed: 6 November 2026).

International Organization for Standardization (2018) ISO 31000:2018 Risk management – Guidelines. Geneva: ISO. Available at: https://www.iso.org/standard/65694.html (Accessed: 6 November 2026).

Kelley, J.E. and Walker, M.R. (1959) ‘Critical-path planning and scheduling’, Papers presented at the December 1-3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference, pp. 160–173. doi:10.1145/1460299.1460318.

Kerzner, H. (2022) Project management: a systems approach to planning, scheduling, and controlling. 13th edn. Hoboken, NJ: Wiley. ISBN 9781119805373.

Kinnison, H.A. and Siddiqui, T. (2013) Aviation maintenance management. 2nd edn. New York: McGraw-Hill. ISBN 9780071805025.

Project Management Institute (2021) A guide to the project management body of knowledge (PMBOK guide) and the standard for project management. 7th edn. Newtown Square, PA: PMI. ISBN 9781628256642.

UK Civil Aviation Authority (2024) Apply for a Part 145 approval. Available at: https://www.caa.co.uk/commercial-industry/aircraft/airworthiness/organisation-and-maintenance-programme-approvals/part-145/apply-for-a-part-145-approval/ (Accessed: 6 November 2026).

AI-Free Assignment Help - Get free Quote
Tell us about your task

Step 1 of 2 · No payment needed to get a quote

Not sure how to fill in this form? Message us on WhatsApp and we will guide you through each field.
Ask on WhatsApp

Need a Custom Answer for Your Assignment?

Get a complete, plagiarism-free solution tailored to your specific requirements and university guidelines.

WhatsApp us